Choose the Alternative that points the right sequence of controlling process:(A) Taking corrective action(B) Setting performance standards(C) Comparison of actual performance with standards(D) Measurement of actual performance(E) Analysing DeviationsChoose the correct answer from the options given below :( – Answer & Explanation | CUET Subject PYQ – Dubuddy

  Choose the Alternative that points the right sequence of controlling process:
(A) Taking corrective action
(B) Setting performance standards
(C) Comparison of actual performance with standards
(D) Measurement of actual performance
(E) Analysing Deviations
Choose the correct answer from the options given below :
(

This question was previously asked in

Shift 30/05/2023 8:30 AM - 10:30 AM

Attempt Online
A
(B), (D), (C), (E), (A)
B
(A), (D), (C), (B), (E)
C
(E), (D), (B), (C), (A)
D
(D), (E), (B), (A), (C)
Correct answer

Correct Answer

(B), (D), (C), (E), (A)
Details icon
Detailed Explanation

(B) Setting performance standards: Prior to the actual performance measurement, it is essential to establish clear and achievable performance standards that define the expected level of performance.

(D) Measurement of actual performance: This step involves the assessment and quantification of the actual performance of the organization or specific activities.

(C) Comparison of actual performance with standards: This step involves comparing the actual performance with the predetermined performance standards to assess the degree of variance and identify areas that require corrective action.

(E) Analyzing deviations: After measuring the actual performance, the next step involves analyzing any deviations or variations from the set standards or expected outcomes.

(A) Taking corrective action: Based on the analysis of deviations, corrective actions are taken to address any issues or discrepancies found in the actual performance.

 